Project Description
Universal Cooling was successful in winning the close control replacement project at Bauer Media. The scope of the project was to completely strip out three old existing dual circuit systems and replace them with a two modern energy efficient systems.
The strip out and installation was phased as to not lose full cooling capacity of the Data Centre. The new condensing units were craned into position located on a roof top plant deck and installed at high level to ensure maximum airflow and optimal operation.
Top return air plenum boxes were installed onto each new indoor unit and the ceiling grid was made good around them.